Construction progress · updated October 2025

Section 3 is 75% complete

The frame is up, façade works and glazing are underway. We show the real status of each section — with photos and work stages.

View photo reports

Section status

Where things stand

The complex is built in phases. Here is where each section stands today.

Section 1Occupied
100%commissioned

Residents have moved in, renovations are complete.

Section 2Occupied
100%commissioned in October 2025

Keys handed over, residents are renovating.

Section 3On sale
75%façade and glazing

14 floor plans with instalments of up to 24 months.

View floor plans →
Section 4Next phase
In preparationsales launch ahead

Floor plans are already known; prices will be revealed before launch.

Join the waiting list →

Section 3 · work stages

What’s done and what’s ahead

  • Excavation and foundationCompleted
  • Monolithic frameCompleted · September 2025
  • External wallsCompleted
  • Façade and glazingIn progress now
  • Internal utilitiesNearing completion
  • Finishing of common areasPlanned
  • Landscaping of the groundsPlanned

For the commissioning date, please check with the sales office — the manager will give you the current date for your apartment.

News archive

Construction updates since 2019

All developer news is published in Ukrainian. Open the news archive →

Follow the progress

A monthly photo report in your messenger

We send photos from the site and the status of work on your section, and give advance notice of price changes.

  • Progress photos of sections 3 and 4
  • Advance notice of price increases
  • Be the first to know about the section 4 sales launch

Fill in the form — or message us, whichever is more convenient.

🔒 Only reports about the complex — no spam or calls outside business hours.